Route 926 Bridge project delayed, but shortened

Last May, area residents learned that the Route 926 Bridge project was to have begun this year. Now it will not happen before next year.

That was the word from Vito Genoa, a consulting engineer for PennDOT.

Work was to have begun after PennDOT finished the Route 52 roundabout project, but Genoa, an engineer with Gannet Fleming Inc., told members of the Chadds Ford Business Association that environmental evaluations required by the federal government, property acquisitions, and working with the utility companies has delayed the start of project. Work could start early in 2016, but more likely in the spring, he said.

Genoa, who worked for PennDOT for 33 years before going to Gannett Fleming 10 years ago, said he’s not sure when the bridge was built, but “its time has come” for replacement.

Vito Genoa, a consulting engineer with Gannet Fleming, fields questions from members of the Chadds Ford Business Association. Genoa was updating members on the Route 926 Bridge and there loop road projects.
Vito Genoa, a consulting engineer with Gannet Fleming, fields questions from members of the Chadds Ford Business Association. Genoa was updating members on the Route 926 Bridge and the loop road projects during a CFBA meeting at the Chadds Ford Historical Society.

The basics of the plan presented last year remain. The bridge, which spans Brandywine Creek between Pocopson and Birmingham townships, and its approaches on Route 926 will be raised — anywhere from 6 to10 feet, according to Genoa — shoulders will be added, new culverts installed over Radley Run, and Creek Road will be relocated a little to the west, closer to the creek.

While the starting date has been postponed, the duration of the project has been speeded up. Instead of taking 18 months as originally planned, the timetable now calls for the job to be done in nine to 10 months.

Picking up the pace of the construction will be accomplished by having the contractor — not yet determined — put in more hours during the day and possibly add weekend work.

Genoa said that instead of having crews work from 8 a.m. to 3 p.m., they could be contracted to work from sunup to sunset.

Once work begins, traffic would be detoured to and from the Route 52 (or Lenape) Bridge or down to Route 1.

The estimated cost is still $12 million to $15 million, Genoa said.

More uncertain is when any action might be taken on the final leg of the loop road project designed to reduce turning traffic through the intersections of Routes 1 and 202.

The two legs of the loop, State Farm Drive and Brandywine Drive, have been open for years, and the Wegmans project includes constructing a third leg.

Genoa noted that all three legs so far have been, or are being, funded by developers, not taxpayers. The same is planned for the fourth leg.

The Henderson Group, which owns the Chadds Ford Business Campus, has offered to build the final leg that would connect the two major routes via Hillman Road, as part of its plans to build a hotel and a restaurant.

However, there’s been no discussion on the matter since an informational meeting at the township building last year.

The Business Association’s next meeting is scheduled for noon, on Thursday, April 7, at Antica restaurant in Chadds Ford Township.

About Rich Schwartzman

Rich Schwartzman has been reporting on events in the greater Chadds Ford area since September 2001 when he became the founding editor of The Chadds Ford Post. In April 2009 he became managing editor of ChaddsFordLive. He is also an award-winning photographer.

1 Star2 Stars3 Stars4 Stars5 Stars (3 votes, average: 5.00 out of 5)
Loading...

Comments

comments

Leave a Reply